DUKE ENERGY OHIO INC.'S PIPP RFP
General

GEN 00001
Published On: 04/11/2016

Question: Do winning CRES bidders win PIPP customers (retail service) or PIPP load (wholesale supply only)?

Answer: The Winning CRES wins the right to serve PIPP load at the wholesale level.  They do not win actual PIPP customers.

GEN 00002
Published On: 04/13/2016

Question: Will the PIPP supplier be responsible for NITS as part of the full requirements service? This is not part of the POLR product.

Answer: The PIPP supplier will not be responsible for NITS charges.

GEN 00003
Published On: 04/13/2016

Question: Is PIPP load served at the meter level?

Answer: The PIPP supplier will enter into a wholesale contract with Duke Energy Ohio to serve the needs of a share of the PIPP customer load.  The obligations for the PIPP supplier are detailed in the Master PIPP Supply Agreement.

GEN 00004 (revised 03/14/2017)
Published On: 04/14/2016

Question: What percentage of the Duke PIPP load is available in the April 2017 RFP?

Answer: 51% of Duke Energy Ohio's PIPP load is up for bid in April 2017.

FAQs Disclaimer
Minimize

FAQs Disclaimer

The information presented and distributed in the Frequently Asked Questions (FAQs) may be subject to modifications and/or amendments and is provided for informational purposes only. The information provided in the RFP, or on the RFP Information Website, has been prepared to assist bidders in evaluating the RFP. It does not purport to contain all the information that may be relevant to a bidder in satisfying its due diligence efforts. Neither Duke Energy Ohio, Inc. nor the PIPP RFP Manager make any representation or warranty, expressed or implied, as to the accuracy or completeness of the information, and shall not, either individually or as a corporation, be liable for any representation expressed or implied in the RFP or any omissions from the RFP, or any information provided to a bidder by any other source. A bidder should check the PIPP RFP Information Website frequently to ensure it has the latest documentation and information. Neither Duke Energy Ohio, Inc., nor the PIPP RFP Manager, nor any of their representatives, shall be liable to a bidder or any of its representatives for any consequences relating to or arising from the bidder’s use of outdated information. The information is not intended to form any part of the basis of any investment decision, valuation or any bid that may be submitted during the RFP process. Each recipient should not rely solely on this information and should make its own independent assessment of the potential value to supply the Duke Energy Ohio, Inc.’s load after making all investigations it deems necessary.

Copyright © 2022 CRA International, Inc.   |   Forward-Looking Statements  |  Privacy Statement  |  Terms Of Use