DUKE ENERGY OHIO INC.'S PIPP RFP

Calendar

Timeline for Duke Energy Ohio, Inc.'s March 2018 PIPP RFP
Delivery Period: June 1, 2018 to May 31, 2019
ActivityDate

Pre-Procurement Activity
Bidder Information SessionWednesday, February 07, 2018
PIPP Supplier Application can be submittedWednesday, February 07, 2018
PIPP Supplier Application is dueThursday, March 01, 2018
Notifications to Registered Bidders including blended SSO price  Thursday, March 08, 2018
March 13, 2018 RFP
Pre-bid security dueFriday, March 09, 2018
Bid window to submit bids (10:00 AM to 02:00 PM ET)Tuesday, March 13, 2018
CRA notifies the Companies and PUCO of results (tentative)Tuesday, March 13, 2018
PUCO acceptance of results (tentative)Wednesday, March 14, 2018
Master PIPP Supply Agreement signed (tentative)Friday, March 16, 2018
Power flowFriday, June 01, 2018
March 19, 2018 Contingency RFP (if necessary)
Pre-Bid security dueFriday, March 16, 2018
Bid window to submit bids (10:00 AM to 02:00 PM ET)Monday, March 19, 2018
CRA notifies the Companies and PUCO of results (tentative)Monday, March 19, 2018
PUCO acceptance of results (tentative)Wednesday, March 21, 2018
Master PIPP Supply Agreement signed (tentative)Friday, March 23, 2018
Power flow)Friday, June 01, 2018